| 30/09/2021 |
Environmental Protection Agency
|
REGION 7 RAF-DES OGALLALA GROUNDWATER CONTAMINATION SITE RI/FS - SOLE SOURCE TO FINISH COMPLETING THE RI/FS REPORTS AT THE SITE. - TOCOR CHANGE |
0 USD |
COST PLUS FIXED FEE |
| 28/09/2021 |
Environmental Protection Agency
|
RAF-DES ORONGO-DUENWEG MINING BELT (ODMB) OU1 RD - TASK ORDER AWARD |
393 673 USD |
COST PLUS FIXED FEE |
| 13/09/2021 |
Environmental Protection Agency
|
REGION 7 RAF-DES OGALLALA GROUNDWATER CONTAMINATION SITE RI/FS - SOLE SOURCE TO FINISH COMPLETING THE RI/FS REPORTS AT THE SITE. |
552 518 USD |
COST PLUS FIXED FEE |
| 19/08/2021 |
Environmental Protection Agency
|
RAF/DES SOUTHWEST JEFFERSON COUNTY SUPERFUND SITE, OPERABLE UNIT 8, MINE WASTE REMEDIAL INVESTIGATION AND FEASIBILTY STUDY |
316 498 USD |
COST PLUS FIXED FEE |
| 11/08/2021 |
Environmental Protection Agency
|
REMEDIAL ACQUISITION FRAMEWORK (RAF), DESIGN AND ENGINEERING SERVICES (DES) - EPA REGION 7 NCMT OU2 RD IMPLEMENTATION SUPPORT - MOD P00004 - KEY PERSONNEL (TASK ORDER MANAGER) CHANGE. |
0 USD |
COST PLUS FIXED FEE |
| 11/08/2021 |
Environmental Protection Agency
|
RAF-DES: ORONOGO-DUENWEG MINING BELT (ODMB) OU1 RD IMPLEMENTATION SUPPORT TASK ORDER AWARD - MOD P00001 KEY PERSONNEL CHANGE - PROJECT MANAGER |
0 USD |
COST PLUS FIXED FEE |
| 17/07/2021 |
Environmental Protection Agency
|
EPA REGION 7 PLATING, INC. SUPERFUND SITE REMEDIAL DESIGN (DES) |
220 991 USD |
COST PLUS FIXED FEE |
| 15/07/2021 |
Environmental Protection Agency
|
REMEDIAL ACQUISITION FRAMEWORK (RAF), DESIGN AND ENGINEERING SERVICES (DES) - EPA REGION 7 NCMT OU2 RD IMPLEMENTATION SUPPORT - MOD P00003 - INCREASE LEVEL OF EFFORT FOR STORM WATER REVIEWS IN THE GRA... |
85 559 USD |
COST PLUS FIXED FEE |
| 24/06/2021 |
Environmental Protection Agency
|
MODIFICATION P00001 TO INCORPORATE A NEW CLIN, ADD NEW FUNDING, REVISE THE STATEMENT ADD A NEW INVOICE APPROVING OFFICIAL. ALL OTHER TERMS AND CONDITIONS REMAIN THE SAME. |
73 165 USD |
FIRM FIXED PRICE |
| 10/06/2021 |
Environmental Protection Agency
|
MISSISSIPPI PHOSPHATE DESIGN IMPLEMENTATION SUPPORT. CONTRACTOR WILL WILL PROVIDE ENGINEERING AND TECHNICAL SUPPORT TO EPA THROUGH COMPLETION OF PHASE 1C COMPLETION. MODIFICATION P00004 IS TO EXERCISE... |
0 USD |
COST PLUS FIXED FEE |
| 11/05/2021 |
Environmental Protection Agency
|
57TH ST AND NORTH BROADWAY RD OPERABLE UNIT 3 (OU3) REMEDIAL DESIGN UNDER REMEDIAL ACQUISITION FRAMEWORK (RAF), DESIGN AND ENGINEERING SERVICES (DES). MODIFICAITON P00004: CHANGE ORDER TO EXERCISE OPT... |
239 311 USD |
COST PLUS FIXED FEE |
| 11/09/2020 |
Environmental Protection Agency
|
THE PROCUREMENT FOR A REMEDIAL DESIGN TASK ORDER FOR THE CRISTEX DRUM SITE. |
451 125 USD |
COST NO FEE |
| 28/08/2020 |
Environmental Protection Agency
|
57TH ST AND NORTH BROADWAY RD OPERABLE UNIT 3 (OU3) REMEDIAL DESIGN UNDER REMEDIAL ACQUISITION FRAMEWORK (RAF), DESIGN AND ENGINEERING SERVICES (DES). MODIFICAITON P00002: CHANGE TOCOR AND ADD SECTION... |
0 USD |
COST PLUS FIXED FEE |
| 22/08/2020 |
Environmental Protection Agency
|
REMEDIAL ACQUISITION FRAMEWORK (RAF), DESIGN AND ENGINEERING SERVICES (DES) - EPA REGION 7 NCMT OU2 RD IMPLEMENTATION SUPPORT - MOD P00002 - ADD FAR 52.204-25 PROHIBITION ON CONTRACTING FOR CERTAIN TE... |
0 USD |
COST PLUS FIXED FEE |
| 21/08/2020 |
Environmental Protection Agency
|
REMEDIAL ACQUISITION FRAMEWORK (RAF), DESIGN AND ENGINEERING SERVICES (DES) - EPA REGION 7 NCMT OU2 RD IMPLEMENTATION SUPPORT - MOD P00001 - REVISED SOW BASED ON PREPROPOSAL CONFERENCE CALL |
0 USD |
COST PLUS FIXED FEE |
| 06/08/2020 |
Environmental Protection Agency
|
REMEDIAL ACQUISITION FRAMEWORK (RAF), DESIGN AND ENGINEERING SERVICES (DES) - EPA REGION 7 NCMT OU2 RD IMPLEMENTATION SUPPORT AWARD |
137 615 USD |
COST PLUS FIXED FEE |
| 27/07/2020 |
Environmental Protection Agency
|
57TH ST AND NORTH BROADWAY RD OPERABLE UNIT 3 (OU3) REMEDIAL DESIGN UNDER REMEDIAL ACQUISITION FRAMEWORK (RAF), DESIGN AND ENGINEERING SERVICES (DES). MODIFICAITON P00001: CHANGE KEY PERSONNEL |
0 USD |
COST PLUS FIXED FEE |
| 29/06/2020 |
Environmental Protection Agency
|
57TH ST AND NORTH BROADWAY RD OPERABLE UNIT 3 (OU3) REMEDIAL DESIGN UNDER REMEDIAL ACQUISITION FRAMEWORK (RAF), DESIGN AND ENGINEERING SERVICES (DES). |
488 185 USD |
COST PLUS FIXED FEE |
| 08/06/2020 |
Environmental Protection Agency
|
THIS TASK ORDER IS FOR DESIGN IMPLEMENTATION SUPPORT FROM THE DESIGNER/ENGINEER OF RECORD (DOR) FOR THE MISSISSIPPI PHOSPHATE SUPERFUND SITE IN PASCAGOULA, MS PHASES 1A, 1B AND 1C. PHASE 1A IS SUBSTAN... |
40 853 USD |
COST PLUS FIXED FEE |
| 02/06/2020 |
Environmental Protection Agency
|
REMEDIAL ACQUISITION FRAMEWORK - RAF, DESIGN AND ENGINEERING SERVICES - DES. THE DES CONTRACT WILL PROVIDE SERVICES TO SUPPORT EPAS CLEANUP PROGRAMS, PRIMARILY THE SUPERFUND PROGRAM. THIS CONTRACT REQ... |
0 USD |
ORDER DEPENDENT (IDV ALLOWS PRICING ARRANGEMENT TO |