Auftragsdetails

Datum
10/05/2018
Auftragswert
0 USD
CPV / PSC
Y1DB
Verfahren
FIRM FIXED PRICE
Land
🇪🇹 ET
Source
USAS

Vergeben an

UNIVERSAL CONSTRUCTION

Vergeben von

Agency for International Development

Beschreibung

IGF::CL::IGF - EXTEND THE TERM OF THE CONTRACT BY 45 DAYS FROM 05/24/2018 TO 07/09/2018 IN ORDER TO COMPENSATE FOR THE TOTAL DAYS OF CONSTRUCTION WORK STOPPAGE. THE WORK STOPPAGE OCCURRED BECAUSE THE USAID/ETHIOPIA ENGINEERING SERVICES AND CONSTRUCTION OVERSIGHT (ESCO) CONTRACTOR, TETRA TECH, PROVIDING THE ARCHITECTURAL AND ENGINEERING (A&E) SERVICES ENCOUNTERED A DELAY IN RENEWING ITS WORK PERMIT AND AS A RESULT THE LIDETA SUB CITY WOREDA 09 ADMINISTRATION OFFICE OF CONSTRUCTION SUPERVISION WITH THE ADDIS ABABA CITY ADMINISTRATION ISSUED A WORK STOP ORDER UNTIL THE WORK PERMIT OF THE A&E CONTRACTOR HAS BEEN RENEWED.